CPUC Draft Resolution E-5455: PG&E service to a 250 MW Google data center in San Jose (pending)

pending

PG&E Advice Letter 7785-E (filed Dec 18, 2025) for Google LLC, 250 MW at 230 kV; the draft of Jul 16, 2026 would approve with modifications, limiting refunds to 100% of annual net revenues and tying network-upgrade costs to the Rule 30 outcome. Held repeatedly; on the Oct 29, 2026 agenda; not adopted as of Oct 21, 2026.

No lobbying positions or financial data recorded for this regulation yet.

Public comment data and advocacy positions are added as they become available.