PUC Order 26-154 (UM 2377): PGE Schedule 96, the data center rate class
challengedOrder entered May 7, 2026 by Chair Letha Tawney and Commissioners Les Perkins and Karin Power. Creates Schedule 96 for data centers of 20 MW and above under HB 3546: minimum transmission and generation demand of 90% of contracted capacity, a flat distribution charge covering all distribution expansion, exit fees and minimum terms, an interconnection queue tied to available emissions-free supply, and a 1 cent/kWh surcharge for Schedule 96 customers of 100 MW or more; adopts the First Partial Stipulation of Feb 4, 2026 (PGE, Staff, AWEC, Amazon, the Data Center Coalition, CUB and others). Compliance tariff approved by Order 26-239 (Jul 10, 2026); reconsideration decided by Order 26-309 (Aug 31, 2026); AWEC petitioned the Court of Appeals on Sept 10, 2026.
- No opposing positions recorded.