Michigan's utility regulator. Approved DTE Electric's contracts for the Saline Township Stargate campus ex parte on Dec 18, 2025 (U-21990), Consumers Energy's large-load terms on Nov 6, 2025 (U-21859) and DTE's contracts for Google's Van Buren Township campus on Oct 1, 2026 (U-22058).

utilitiestech ai

Tracked direct giving

$0

Tracked donations to candidate

$0

Connections

3

Connection Graph
0 nodes · 0 edgesHover for labels · Double-click to expand
Loading graph...
Person
Organization
PAC
Gov Body
Legislature
Think Tank
Industry
Outcome

Click a node to see details

Double-click to expand its connections

Regulatory Capture Assessment

Regulatory capture occurs when a regulatory agency advances the interests of the industry it is meant to oversee. The indicators below track evidence of capture for this agency. According to the academic literature (Stigler 1971, Carpenter & Moss 2013), captured agencies exhibit declining enforcement, revolving door personnel pipelines, and rule-making that favors incumbents over public interest.

Industry connections
0
Enforcement actions
0
Revolving door
0
View all tracked agencies →

Relationships

TypeConnected ToDetailsSource
issued_ruleMPSC U-22058: DTE Electric's contracts for Google's Van Buren Township data center, approved after a contested caseApproved DTE Electric's contracts for Google's Van Buren Township campus after a contested case, Oct 1, 2026.Source
issued_ruleMPSC U-21990: ex parte approval of DTE Electric's contracts for the Saline Township Stargate campus (1,383 MW)Approved DTE Electric's contracts with Green Chile Ventures (Oracle) ex parte, Dec 18, 2025.Source